Installing an Additional Power Supply for NX-7510 or NX-7530 Integrated Services Platform
To install an additional power supply for an NX-7510 or NX-7530
integrated services platform:
-
Unpack the AC or DC power supply module and
carefully insert it into the NX-7510 or NX-7530 integrated services
platform.
-
When installing a second power supply in an NX-7510 or NX-7530 integrated
services platform, remove the blank cover from the back.
-
Press the locking latch to lock the power supply in place.
-
Plug the power cord into the power supply.
-
Observe that the power supply light is illuminated to verify that the power
supply is operating properly.

Note
When two power supplies are installed, both power supplies should be
properly connected to a power source and powered up. An audible beep and
display of a red LED indicates that a power supply is not properly connected
to a power source.