When your stack is operational, one switch is the primary switch, responsible for running network protocols and managing the stack.
To provide recovery in case of a break in the stack connections, you can configure redundancy by designating a backup switch to take over as primary if the primary switch fails. When you perform the initial software configuration of the stack, the “easy setup” configuration option automatically configures redundancy, with slot 1 as the primary and slot 2 as the backup. You can also configure additional switches as “primary-capable,” meaning they can become a stack primary in case the initial backup switch fails.
X695 and X465 switches can be combined in the same stack. When you assign the primary and backup roles in a mixed stack, consider the feature scalability and the speed of each switch model. The easy setup configuration process selects primary and backup switches based on capability and speed. The following list shows the switches in order of capability, with the most capable switch first:
For example, in a stack that combines X695 and X465 switches, an X695 switch might support higher scale limits for some features than an X465 switch. Consider these differences when selecting a primary node, selecting a backup node, and configuring failover operation.

Note
Assign the primary and backup roles to switches from the same series. For example, if the primary node is an X695 switch, the backup node should also be an X695 switch.When easy setup compares two switches that have the same capability, the lower slot number takes precedence.
Follow the same ranking hierarchy when you plan the physical placement of the switches in the stack.