Install Your Switch

Before you begin

Before you attempt to install or remove an Extreme Networks switch, read the precautions in Safety Considerations for Installation.

About this task

Extreme Networks switches fit into standard 19-inch equipment racks. A two-post rack-mounting kit is provided with the switch.

The installation process includes the following tasks:

Procedure

  1. Prepare to install the switch.
  2. Mount the switch, or install the switch in the rack.
  3. Connect network interface cables.
  4. Install optional components: optical transceivers and cables.
    See the instructions in Install Optional Components.
  5. Power up the switch.
  6. Perform initial network connection and configuration.