Installing the DC Power Supply
After preparing the DC cables, install the DC
power supply (Model 10933 or 10934A) in the E4G-400 router.
-
If necessary, remove a blank panel as shown in
the following figure.
-
Verify that the power supply is right side up, and
slide it into the router.
-
Carefully slide the power supply all the way into
the power supply bay, as shown in the figures below, until the latch snaps into
place.
![Caution](../../images/Caution_Note.png)
Caution
Do not slam the power supply into the
router.
Installing a Summit 300 W DC Power Supply
(Model 10933)
Installing a Summit 300 W DC Power Supply
(Model 10934A)
If power supplies are not installed in both power supply bays,
install a cover over the unoccupied bay. The cover is required for maintaining
proper system ventilation and EMI levels.